Tolerance Stack-Up on a Napkin: A Worked 4-Part Example

A simple tolerance stack-up analysis needs four things: a loop drawn from one surface back to itself, a plus or minus sign on every dimension in that loop, the sum of the nominals, and the sum of the tolerances. That's worst case, and for an assembly of four parts it fits on a napkin in ten minutes. Below is the exact example I'd sketch for a founder, including the part where the first answer fails and how I'd fix it without paying for tighter tolerances everywhere.

I'll use one linear stack, because most real problems I see are exactly that: parts sitting in a row inside a housing, and a gap at the end that has to stay inside a window.

The assembly and the question

Picture a small gearbox. A machined aluminium housing has a pocket. Inside it, along one axis, sit three parts: a steel spacer, a moulded POM gear hub, and a bronze bushing. A retaining face closes the pocket. The question is the axial end play, the gap between the bushing and the closing face.

The requirement: end play between 0.20 and 0.60 mm. Less than 0.20 and the gear binds when the POM grows with heat and moisture. More than 0.60 and it rattles and the mesh walks.

Here are the drawing dimensions as first proposed:

PartDimensionDirection in loop
Housing pocket depth37.50 ±0.10+
Spacer length12.00 ±0.05−
Gear hub length15.00 ±0.08−
Bushing length10.00 ±0.05−

Draw the loop before you add anything

This is the step people skip, and it's where most napkin stack-ups go wrong.

Start at the bushing's free face, the one that defines the gap. Walk through the assembly, one contact at a time, until you come back to the other side of the gap. Every dimension you cross going "right" gets a plus, every one going "left" gets a minus. In this case the pocket depth pushes the closing face away (plus), and each part in the pocket eats into that space (minus).

If you can't draw the loop through actual contacting surfaces, your drawing is dimensioned from the wrong datums, and no amount of arithmetic will save it. I've written more about that in the manufacturing drawing checklist, but the short version is that the dimension on the drawing should be the one the stack needs, face to face, not a chain of three dimensions from some unrelated edge.

Worst case, in four lines

Nominal gap: 37.50 − 12.00 − 15.00 − 10.00 = 0.50 mm.

Worst-case tolerance: 0.10 + 0.05 + 0.08 + 0.05 = 0.28 mm. Signs don't matter here, tolerances always add.

So the gap runs from 0.22 to 0.78 mm.

The minimum's fine. The maximum blows through 0.60 by almost 0.2 mm, which on a gear that's 15 mm long is enough to hear. The design fails worst case, and the nominal is also sitting off-centre in the window (0.50 against a midpoint of 0.40), which is a second, quieter problem.

The RSS answer, and why I don't trust it here

The statistical version, root sum of squares, assumes every dimension is normally distributed, centred on nominal, and independent. Square each tolerance, add them, take the square root:

√(0.10² + 0.05² + 0.08² + 0.05²) = √0.0214 ≈ 0.146 mm.

That gives 0.35 to 0.65 mm. Still over the top limit, but only just, and it's tempting to shrug and ship.

Don't. RSS earns its keep when you've got many contributors and a supplier whose process is centred and stable. With four parts, a first production batch of a few hundred units and a moulded part whose length depends on shrinkage that nobody has measured yet, the assumptions are wishful. A moulded hub tends to come out consistently long or consistently short, not scattered around nominal. My rule of thumb: under five or six contributors, or anything that can injure someone or jam a mechanism, I design to worst case and use RSS only as a sanity check on how often I'd actually see the extremes.

Fixing it without tightening everything

The lazy fix is to tighten every tolerance until the sum fits. That works on paper and costs money on every part forever. Better to ask which number is cheapest to move.

First, re-centre the nominal. The window midpoint is 0.40, so drop the pocket depth to 37.40. Now the nominal gap is 0.40 and you've got 0.20 of room either side.

Second, find 0.08 mm of tolerance to remove (0.28 down to 0.20). The pocket depth is a single milled face; holding ±0.05 on that is routine on a CNC and usually adds nothing to the price. The gear hub is the expensive one to tighten, because a moulder holding ±0.05 on 15 mm of POM is asking for tool tuning. So I'd leave the hub alone at ±0.08 and look for the last 0.03 elsewhere: the steel spacer can go to ±0.02 if it's turned, which is cheap on a lathe.

New worst case: 0.05 + 0.02 + 0.08 + 0.05 = 0.20. Gap 0.20 to 0.60. It fits, exactly, and only the two machined parts changed.

What I'd actually do on a real product

Honestly? I'd probably not fight the stack at all. I'd put a wave spring or a thin wave washer between the bushing and the closing face, size the pocket so the spring is always partly compressed, and let it absorb anything from 0.1 to 0.8 mm. Every tolerance in the stack goes back to a comfortable general value, and the moulder stops being the critical path.

Last year a founder brought me a nearly identical stack on a small motorised device. The team had spent two rounds with their moulder trying to hold a plastic length to ±0.03, and parts were still out. A 0.3 mm wave washer and a 0.2 mm deeper pocket solved it, and the hub went back to an ordinary tolerance. The fix cost less than one of those tool adjustment rounds.

The counter-intuitive bit: tight tolerances are often a sign the design is asking the parts to do a job a spring should do.

When a stack does have to be held by the parts themselves (sealing faces, optical alignment, anything where compliance isn't allowed), that's where precision machining earns its price. In my earlier microfluidics work we held CNC assembly tolerances around 5 micrometres, and every one of those stacks started with a loop drawn on paper exactly like this one.

When the napkin isn't enough

The napkin method covers one-dimensional stacks: parts in a line, gaps along one axis. It breaks down when angles enter the loop (a tilted face, a hinge, a hole pattern that can rotate), when geometric tolerances such as position and perpendicularity contribute, or when you have more than about ten contributors. Then I build the stack in a spreadsheet with sensitivity factors, or model the worst-case positions in CAD and measure them.

That's normal work in mechanical design and 3D modeling, and it's one of the first things I check in a DFM review, because a stack that only works at nominal tends to show up as a field return six months after launch.

If you've got an assembly with a gap that worries you, send the drawings and the requirement. You can request a free initial DFM review of one part or assembly, and I'll tell you whether the stack closes and which single dimension is cheapest to change if it doesn't.

Questions people ask

What is the difference between worst-case and RSS tolerance stack-up?

Worst case adds every tolerance at its limit, so the result always holds. RSS adds the squares and takes the square root, which predicts the range most assemblies will fall in, assuming centred and independent processes. RSS gives a narrower result but can be optimistic for few parts or uncentred processes.

How do I handle unequal tolerances like +0.10/-0.00?

Convert them to an equal bilateral tolerance around a shifted nominal before you add anything. For example, 15.00 +0.10/-0.00 becomes 15.05 ±0.05. The arithmetic then works the same as for every other line.

Which tolerance should I tighten first?

The one that's cheapest to hold, which is usually a single machined face or a turned length. Moulded and sheet metal dimensions are expensive to tighten. Re-centring the nominal often helps more than tightening anything.

When do I need software instead of a hand calculation?

When the loop includes angles, geometric tolerances such as position, or more than about ten contributors. A spreadsheet with sensitivity factors or a CAD-based check is then more reliable than a single sum.